Margen Impex
Limited
believes in total quality systems. We believe that the final
product that reaches the customer can be of the first quality only when the
procedure laid then by the company is strictly followed at all the stages from
the beginning.
The quality
system that we adhere at the following stages:
Incoming materials
Welders qualification.
-
Identification of Raw material.
-
Stage-wise inspection.
-
Radiography.
-
Dimensional inspection.
-
Hydro test.
-
Painting, Packing etc.
-
Documentation.
1.INCOMING
MATERIALS :
All incoming materials are classified into three categories : 'A', 'B' & 'C',
'A' category materials are all raw materials like plates, pipes, tubes etc. 'B'
category materials like flanges, fasteners, gaskets, welding consumables where
as 'C' category for all the other good that is required generally.
All 'A' category
materials are inspected for surface finish, size & then sent for check
testing to a reputed laboratory. If third party inspection is involved the
sample material is sent with the stamp of third party inspector. A register is
maintained for all the raw materials & identified with check test number. The
check test number is stamped on all the components of the job.
'B' category materials
are inspected visually & accepted on the basis of manufacturer's test
certificates. All 'C' category materials are inspected visually & accepted.
A separate stores
Inspection report memo is prepared by the stores incharge & release to the shop
only after the report is signed by the Quality control engineer.
2. WELDERS
QUALIFICATION :
All welders are given the nos. like W3, W4, etc. A separate register is
maintained for WPS & PQR. Both WPS & PQR are prepared in the printed format &
after the successful qualification these records are endorsed by the third party
inspector. A separate file is maintained for these records.
3.
IDENTIFICATION OF RAW MATERIAL :
A separate inspection report is prepared in the printed format giving all the
details of the job, the component, the raw material size, physical & chemical
properties as well as the heat treatment involved. The each component is having
the details of quality of material, part number, & heat/check test No & the
stamp of the third party inspector.
4.
STAGE-WISE INSPECTION :
The in-process stages like set-ups, back chips, fit-ups etc are recorded with
all the observations in the stage-wise inspection report book before offering
the same to the third inspector.
5.
RADIOGRAPHY :
A radiography sketch of the equipment giving details of all the weld joints is
prepared in advance & after the radiography is taken they are marked in the
sketch. The radiography technique, the source strength, the film details and the
joint details. After the films are viewed the remarks are entered & then offered
fir the third party inspector for his review.
6.
DIMENSIONAL INSPECTION :
When the equipment is completed in all aspects before hydro test the final
dimensions are checked & noted on the drawing as well as a report is prepared.
Any major deviation observed are corrected, if not possible, conveyed to the
client/consultant for their approval.
7. HYDRO
TEST :
Hydro test is carried out on the equipment after all the clearances are obtained
for NDT, dimensional, materials etc.
The equipment is
positioned in such way so that no airlock is created. Two pressure gauges are
used which are calibrated. All the weld joints as well as the joints are
thoroughly cleaned. Holding time is minimum of 30 minutes. A separate Inspection
report is prepared & enclosed by the third party Inspector.