| FABRICATION OF THE
FOLLOWING |
- M.S. & S.S. Piping - Shop Fabrication
- M.S. & S.S. sheet metal Structure in light /
medium / heavy.
- Tanks, Vessels, Equipments, etc. in M.S. &
S.S.
- Plate & Pipe Bending job
|
| OTHER |
- FLANGES : M.S & S.S Flanges as per IS, ASA,
ND & BS standards.
- Precision Machining Jobs : Machining part as
per client drawing / design etc.
- Equipment Electrical Assembly : Cable Harness
assembly, Control System Assembly, Electrical Cabinet
Assembly as per design / drawing
|
| TESTING
FACILITIES: |
| Through External Agencies for: |
- NDT
- RADIOGRAPHY
- ULTRASONICS
- STRESS RELIEVING.
|
| QUALITY
CONTROL: |
| Stagewise Inspection INTERNAL / EXTERNAL Agencies as
required. |
| QUALITY ASSURANCE
SYSTEM |
|
Margen Impex Limited believes in total quality systems. We
believe that the final product that reaches the customer
can be of the first quality only when the procedure laid then
by the company is strictly followed at all the stages from the
beginning |
The quality system that we adhere at the following
stages:
- Incoming materials
- Welders qualification.
- Identification of Raw material.
- Stage-wise inspection.
- Radiography.
- Dimensional inspection.
- Hydro test.
- Painting, Packing etc.
- Documentation.
|
| 1. INCOMING MATERIALS
: |
All incoming materials are classified
into three categories : 'A', 'B' & 'C', 'A' category
materials are all raw materials like plates, pipes, tubes etc.
'B' category materials like flanges, fasteners, gaskets,
welding consumables where as 'C' category for all the other
good that is required generally.
All 'A' category materials are inspected for surface
finish, size & then sent for check testing to a
reputed laboratory. If third party inspection is involved the
sample material is sent with the stamp of third party
inspector. A register is maintained for all the raw materials
& identified with check test number. The check test number
is stamped on all the components of the job.
'B' category materials are inspected visually &
accepted on the basis of manufacturer's test certificates. All
'C' category materials are inspected visually &
accepted.
A separate stores Inspection report memo is prepared by
the stores incharge & release to the shop only after the
report is signed by the Quality control engineer.
|
| 2. WELDERS QUALIFICATION
: |
| All welders are given the nos. like W3,
W4, etc. A separate register is maintained for WPS & PQR.
Both WPS & PQR are prepared in the printed format &
after the successful qualification these records are endorsed
by the third party inspector. A separate file is maintained
for these records. |
| 3. IDENTIFICATION OF RAW
MATERIAL : |
| A separate inspection report is prepared
in the printed format giving all the details of the job, the
component, the raw material size, physical & chemical
properties as well as the heat treatment involved. The each
component is having the details of quality of material, part
number, & heat/check test No & the stamp of the third
party inspector. |
| 4. STAGE-WISE INSPECTION
: |
| The in-process stages like set-ups, back
chips, fit-ups etc are recorded with all the observations in
the stage-wise inspection report book before offering the same
to the third inspector. |
| 5. RADIOGRAPHY
|
| A radiography sketch of the equipment
giving details of all the weld joints is prepared in advance
& after the radiography is taken they are marked in the
sketch. The radiography technique, the source strength, the
film details and the joint details. After the films are viewed
the remarks are entered & then offered fir the third party
inspector for his review. |
| 6. DIMENSIONAL INSPECTION
: |
| When the equipment is completed in all
aspects before hydro test the final dimensions are checked
& noted on the drawing as well as a report is prepared.
Any major deviation observed are corrected, if not possible,
conveyed to the client/consultant for their
approval. |
| 7. HYDRO TEST
: |
Hydro test is carried out on the
equipment after all the clearances are obtained for NDT,
dimensional, materials etc.
The equipment is
positioned in such way so that no airlock is created. Two
pressure gauges are used which are calibrated. All the weld
joints as well as the joints are thoroughly cleaned. Holding
time is minimum of 30 minutes. A separate Inspection report is
prepared & enclosed by the third party
Inspector. |